I want to paste-link a Prism 3 graph into Microsoft Excel, but it doesn't work.
Using Prism 3.02 and Excel 2000 SP1, we've noted that Paste Link doesn't work. But it works fine to paste-link a Prism graph into Word or PowerPoint. We don't know why Excel doesn't work the same way. All we can suggest is that you use Word as the master document and paste both Excel and Prism into it. Or paste-embed from Prism, which works fine.
This was fixed in Prism 4.